A practical RFQ checklist for getting accurate CNC machining quotes, comparing suppliers and avoiding delays, misunderstandings and unexpected costs.

⚡ Quick Answer

A complete CNC machining RFQ should include the part drawing and CAD file, material and grade, quantity, critical tolerances, GD&T, surface finish, heat treatment, secondary processes, inspection requirements, packaging, delivery requirements and any applicable certifications.

The Essentials

CNC Machining RFQ Checklist

The minimum set of items a CNC manufacturer needs to return an accurate, comparable quotation. Use this table as your pre-send verification.

RFQ ItemRequired?Why It Matters
3D CAD fileRecommendedDefines geometry
2D drawingStrongly recommendedDefines dimensions & tolerances
MaterialRequiredDetermines cost and process
Material gradeRequiredPrevents material assumptions
QuantityRequiredDrives unit cost
Annual volumeRecommendedEnables production pricing
ToleranceRequiredDetermines process capability
GD&TWhen applicableDefines functional requirements
Surface finishWhen applicableAffects processing & cost
Heat treatmentWhen applicableAdds process requirements
Plating / anodizingWhen applicableAdds finishing cost
InspectionWhen applicableDefines QC scope
CertificationWhen applicableAdds documentation requirements
PackagingWhen applicableAffects final cost
Delivery dateRecommendedDetermines production planning
Completeness

Is Your CNC RFQ Complete?

The more complete your RFQ, the fewer assumptions a manufacturer has to make when pricing your part — and the more comparable your supplier quotes become.

Basic RFQ

Moderate Accuracy

CAD + Quantity + Material

  • Geometry from CAD only
  • Material named, grade assumed
  • No tolerances specified
  • Supplier must clarify before quoting
Quote Accuracy: Moderate
Standard RFQ

High Accuracy

CAD + 2D Drawing + Material + Quantity + Tolerance + Finish

  • Dimensions and tolerances defined
  • Material grade specified
  • Finish and critical tolerance stated
  • Minor clarification may remain
Quote Accuracy: High
Production RFQ

Highest Accuracy

CAD + Drawing + Material + GD&T + Finish + Inspection + Packaging + Delivery + Annual Volume

  • Full manufacturing definition
  • Inspection and documentation set
  • Logistics and volume defined
  • Quotes are directly comparable
Quote Accuracy: Highest

RFQ Readiness Score

Tick the items you already have prepared. A complete package (all ticked) is ready for comparable supplier quotations.

3D CAD model✓ Ready
2D manufacturing drawing✓ Ready
Material & grade specified✓ Ready
Quantity & annual volume✓ Ready
Critical tolerances / GD&T✓ Ready
Surface finish defined✓ Ready
Inspection requirements✓ Ready
Target delivery date✓ Ready
85%
Typical complete-RFQ score
Background

What Is a CNC Machining RFQ?

An RFQ, or Request for Quotation, is the technical and commercial information a buyer sends to a CNC manufacturer so the supplier can determine manufacturing cost, process requirements, lead time and quality requirements.

RFQ vs RFP vs Purchase Order

DocumentPurpose
RFQAsk supplier for price and lead time
RFPRequest a broader proposal
POAuthorize the purchase
Step 1 of 12

1. 3D CAD File

The 3D model is the foundation of any CNC quote — it defines the part geometry the shop will machine.

Neutral formats

Preferred for quoting

STEPSTPIGESParasolid (X_T)

Native CAD

Where appropriate

SolidWorksOther native

Why it matters

Geometry only

  • Defines shape and features
  • Enables machining simulation
  • Not a substitute for the drawing
Note: The 3D model defines geometry, but it may not contain all manufacturing requirements — that is the job of the 2D drawing.

Goldcattle accepts STEP / IGES / X_T / SolidWorks files for engineering review and quotation. See the CNC Machining Services page for full capability details.

Step 2 of 12

2. 2D Manufacturing Drawing

A 2D drawing translates the model into measurable, inspectable manufacturing requirements. It is where tolerances, threads and finish live.

Dimensions

  • Overall dimensions
  • Critical dimensions
  • General tolerance block

Features

  • Tolerances
  • GD&T (datums & symbols)
  • Thread specifications
  • Hole callouts

Requirements

  • Surface finish (Ra)
  • Material & grade
  • Heat treatment
  • Coating / plating
  • Revision & notes

Sample CNC Drawing

120 ±0.02 80 ⌀10 H7 6061-T6 REV B Clear Anodize, Type II ⌓ 0.05 1 2 3 4 5

What each callout shows

  1. Material6061-T6 defines alloy and temper — not just "aluminum".
  2. Critical tolerance±0.02 mm on the controlled dimension, not on every feature.
  3. Surface finishClear anodizing, Type II — specifies treatment, not just "anodized".
  4. GD&TFlatness 0.05 mm referenced to a datum for function.
  5. RevisionREV B ensures the shop quotes the current design.
Step 3 of 12

3. Specify the Exact Material and Grade

Do not write only “Aluminum”. State the alloy and temper so the shop prices the correct stock and process.

Aluminum

6061-T67075-T62024-T3

Stainless Steel

304316L17-4 PH

Plastics

PEEKPOMPA66PCABS
Material grade affects machining behavior, mechanical properties, surface finish, cost and certification requirements. “Aluminum 6061-T6” is far more precise than “Aluminum”.
Step 4 of 12

4. Specify Quantity and Annual Volume

Quantity is the order you place now. Annual volume is total demand across the year — and the two are not the same.

Quantity InformationExample
Prototype5 pcs
Initial production100 pcs
Batch size500 pcs
Annual demand10,000 pcs
Example: Initial order 100 pcs / Annual volume 5,000 pcs. Suppliers may quote differently depending on whether 100 pieces is a one-time order or part of a 20,000-piece annual program.
Step 5 of 12

5. Specify Critical Tolerances

Mark only the dimensions that are functionally critical. A blanket tight tolerance on every feature raises cost without adding value.

RequirementWhat Buyer Should Provide
General tolerancee.g. ISO 2768
Critical toleranceExact value
GD&TDatum + tolerance
HoleDiameter + tolerance
ThreadThread standard + class
FlatnessMaximum allowed deviation
PositionPosition tolerance

Don’t Over-Specify Tolerances

Tighter tolerance → more machining and inspection time → higher cost. Reserve tight tolerances for features that affect fit, function or assembly.

General tolerance Low cost
Critical tolerance Medium cost
Special inspection Higher cost
Higher overall cost +
Rule of thumb: specify ±0.005 mm only where the function requires it. For everything else, use a general tolerance standard and let the shop apply standard process capability.

Related: CNC Machining Tolerance Guide

Step 6 of 12

6. Specify Surface Finish and Cosmetic Requirements

Separate surface roughness, surface treatment and cosmetic acceptance — “black anodized” alone rarely defines the required finish.

Surface roughness

Measured value

Ra 0.8 µmRa 1.6 µmRa 3.2 µm

Surface treatment

Process + class

AnodizingHard anodizingElectroless nickelPassivationPowder coatingZinc platingBlack oxideBead blasting

Cosmetic requirements

Visible surfaces

  • Visible vs hidden faces
  • No scratches / dents
  • No tool marks
  • Color consistency
Step 7 of 12

7. Include Heat Treatment Requirements

If the part needs heat treatment, state it explicitly — it changes material behavior and may affect final dimensions.

T6T651AnnealingStress relievingHardening
Note: Heat treatment may affect dimensions and therefore should be considered before final inspection.
Step 8 of 12

8. Secondary Operations

List any processes beyond machining so the supplier prices them and plans capacity.

Finishing

  • Anodizing / plating
  • Painting
  • Grinding

Assembly

  • Press-fit
  • Insert installation
  • Sub-assembly

Other

  • Deburring
  • Laser marking
  • Hardware sourcing
Step 9 of 12

9. Define Your Inspection Requirements

Don’t simply write “100% inspection.” Define what needs to be inspected and what report is required.

Basic

  • Final dimensional inspection

Advanced

  • CMM inspection
  • FAI (First Article)
  • Material certificate
  • Surface roughness report

Automotive / Aerospace / Medical

  • PPAP
  • FAI
  • Traceability
  • Specific documentation
Clear inspection scope lets the supplier quote the right QC effort and return evidence you can act on — instead of an ambiguous promise.
Step 10 of 12

10. Specify Required Certifications and Documents

State the certificates and documents your quality system or application requires. Only request what you can actually verify and use.

Quality system

ISO 9001

Compliance

RoHSREACH

Material & part docs

Material certificateCoCFAIEN 10204 3.1
Accuracy matters: Only list certifications the supplier can genuinely provide and document. Requesting PPAP or FAI should match a real automotive / aerospace / medical requirement — not as a generic checkbox.
Step 11 of 12

11. Specify Packaging Requirements

For high-precision parts, packaging prevents scratches, deformation and corrosion — and it affects final cost.

Individual baggingFoamAnti-scratchAnti-corrosionTrayExport cartonPalletBarcodePart numberLot number
Step 12 of 12

12. Include Lead Time and Shipping Requirements

Avoid “Need ASAP.” Give a real target date and shipping terms so the supplier can plan production.

Example targets

  • Prototype: 7 business days
  • Production: 20 business days

Incoterms & shipping

EXWFOBCIFDAPDDP
AirExpressSea

See Goldcattle delivery information on the CNC Machining Services page.

Worked Example

Example of a Complete CNC Machining RFQ

Part: Aluminum CNC Housing
Material: 6061-T6 aluminum
Quantity: 100 pcs initial order / 2,000 pcs annual volume
Process: CNC milling + drilling + tapping
Critical tolerance: ±0.02 mm
Hole tolerance: Ø10 H7
Surface finish: Ra 1.6 µm
Finish: Clear anodizing, Type II
Inspection: CMM for critical dimensions
Documentation: Material certificate + inspection report
Packaging: Individual protective packaging
Delivery: Prototype within 7 business days; production within 20 business days
Files: STEP + PDF drawing, Rev B

What This RFQ Allows the Manufacturer to Quote

Machining timeToolingMaterialFinishingInspectionPackagingLead timeShipping
Comparison

Weak RFQ vs Complete RFQ

⚠ Weak RFQ

“Hello, please quote 100 aluminum parts. See attached drawing.”
  • No material grade
  • No quantity context
  • No finish
  • No inspection
  • No delivery requirement
  • No annual volume

✓ Complete RFQ

Aluminum 6061-T6 housing, 100 pcs + 2,000/yr, ±0.02 mm, Ø10 H7, Ra 1.6, clear anodize II, CMM on critical dims, individual pack, prototype 7 / production 20 days. STEP + PDF Rev B.
  • Material grade defined
  • Quantity + annual volume
  • Finish specified
  • Inspection defined
  • Delivery target given
  • Files attached
A complete RFQ produces more comparable quotations and reduces clarification cycles.
Avoid These

10 Common CNC RFQ Mistakes

1
Sending only a screenshotA picture cannot be machined or measured.
2
Omitting material grade"Aluminum" leaves the alloy and temper to chance.
3
Not specifying quantityNo quantity means no unit-cost basis.
4
Treating every dimension as criticalUnnecessary cost from over-tight tolerances.
5
Missing surface finishFinish drives process and cost.
6
Not specifying inspectionUnclear QC scope and reporting.
7
No drawing revisionRisk of quoting the wrong version.
8
No annual volumeMisses production-pricing opportunity.
9
Saying "ASAP" instead of a deadlineA date enables real planning.
10
Comparing quotes with different assumptionsOnly comparable RFQs yield comparable quotes.
Budgeting

Which RFQ Requirements Affect CNC Machining Cost?

RequirementCost Impact
MaterialHigh
QuantityVery High
Tight toleranceHigh
Complex geometryHigh
5-axis machiningHigh
Surface finishingMedium–High
Heat treatmentMedium
InspectionMedium
PackagingLow–Medium
Delivery urgencyHigh
Quantity and manufacturability often influence cost more than individual cosmetic requirements. Related: How Much Does CNC Machining Cost?
Need Help Preparing Your RFQ?

How Goldcattle Handles a CNC RFQ

Upload your CAD and drawing — Goldcattle’s engineering team reviews the project, gives DFM feedback and returns a quotation.

1
Upload CAD + DrawingYou send files
2
Engineering ReviewFeasibility check
3
DFM FeedbackDesign for manufacture
4
Material / ProcessConfirm specs
5
QuotationTransparent pricing
6
PrototypeFirst samples
7
InspectionDimensional check
8
ProductionScale to volume
9
Final InspectionQC before ship
10
ShipmentDeliver to you

What Should You Send Goldcattle?

1

3D CAD

STEP / IGES / Parasolid / SolidWorks

2

2D Drawing

PDF with dimensions and tolerances

3

Material

Grade + temper

4

Quantity

Prototype + production + annual volume

5

Finish

Anodizing / plating / coating / etc.

6

Critical Requirements

Tolerance / GD&T / inspection

Get Started

Get a CNC Quote

Upload your CAD, drawing and specifications. Our engineering team reviews the project, identifies manufacturing requirements and provides a quotation.

Questions Buyers Ask

Frequently Asked Questions

What files should I send for a CNC machining quote?

Send a 3D CAD file (STEP, IGES, Parasolid or native SolidWorks) and a 2D manufacturing drawing in PDF. Together they define geometry, dimensions, tolerances and finish requirements.

Is a 3D CAD file enough for a CNC RFQ?

A 3D model defines geometry but may not contain all manufacturing requirements such as tolerances, GD&T, thread specs and surface finish. A 2D drawing is strongly recommended.

Do I need a 2D drawing?

Yes, where dimensions and tolerances matter. The 2D drawing defines critical dimensions, tolerances, GD&T, threads, surface finish and revision control that the CAD model alone may not convey.

What material information should I include?

Specify both the material and the exact grade and temper, for example “Aluminum 6061-T6” rather than just “Aluminum”. Grade affects machining behavior, mechanical properties, finish and cost.

Should I specify every tolerance?

No. Use a general tolerance standard (e.g. ISO 2768) for non-critical features and specify exact values only for critical dimensions. Over-tight tolerances increase machining and inspection cost.

What is the difference between quantity and annual volume?

Quantity is the size of the order you are placing now; annual volume is the total demand across a year. Suppliers quote differently depending on whether 100 pieces is a one-off or part of a 20,000-piece program.

Should I include surface finish in my RFQ?

Yes. Specify both surface roughness (e.g. Ra 1.6) and any treatment (anodizing, plating, passivation) plus visible-surface cosmetic requirements.

Do I need to specify inspection requirements?

Define what must be inspected and what report is required (final inspection, CMM, FAI, material certificate) rather than writing “100% inspection”, which is ambiguous.

Should I request CMM inspection?

Request CMM inspection for critical dimensions and for first-article or production parts where traceable dimensional data is required.

Do I need material certificates?

Request material certificates (such as EN 10204 3.1) and a CoC when the application or your quality system requires documented material traceability.

What information affects CNC machining cost the most?

Quantity and manufacturability usually influence cost most, followed by material, tight tolerances, complex geometry, 5-axis requirements, surface finishing and inspection scope.

How long does it take to receive a CNC quote?

A complete RFQ can typically be quoted within 1–2 business days. Incomplete RFQs take longer because the supplier must request clarification before pricing.

Can I submit an RFQ without knowing the exact manufacturing process?

Yes. Provide the part requirements (geometry, material, tolerance, finish, volume) and the manufacturer can recommend the appropriate process (3-axis, 5-axis, turning or milling).

Build a Complete CNC Sourcing Library

This RFQ guide works best alongside Goldcattle’s other CNC resources — each one feeds back to a single action: request a quote.

Upload Your CAD for a CNC Quote

Send your 3D CAD, 2D drawing, material and quantity. Our engineering team will review the project, identify manufacturing requirements and provide a quotation.

Recommended Reading