Case study / Tool build

32-Cavity Injection Mold for a Slim Tubular Part

A production tool for a thin-wall part, built as one matched core and cavity set. This record covers what the drawing asked for, where the build was difficult, and how the steel and the first samples were measured before the tool was released.

Cavities
32Four columns of eight, one block
Tool steel
Hardened tool steelGrade fixed in the order
Cavity work
±0.01 mmOn the dimensions marked on the tool drawing
Verification
CMM plus trial samplesEvery cavity on the same datum
Mold making capabilities
Tool build Two halves of a 32-cavity injection mold standing on a stainless steel bench, one plate with slender elongated cavities and the other with matching long cores, guide pillars, water fittings and lifting eyes visible

Customer name, part drawing, resin grade and order volumes stay in the project file. What is published here is the tool, the build sequence and the inspection method.

01

Project at a glance

The record in one block. Each line was agreed at order and checked before the tool was released.

Tool type
Two-plate injection mold, cold runner, one part per cavity
Cavity count
32, arranged four columns by eight rows
Part
Slim tubular part, thin wall, long coreWall thickness and length are set by the customer drawing
Cavity steel
Hardened tool steel, grade and hardness range fixed in the order
Cavity tolerance
±0.01 mm on the cavity dimensions marked on the tool drawingNot a blanket tolerance for every surface
Core and cavity
Machined and measured as a matched pair
Working surfaces
Polished in the draw direction, edges protected
Cooling
Circuits on both sides, core cooled from the inside
Guiding
Four guide pillars into bushed bores in the opposite plate
Handling
Lifting eyes on both plates
Trial
T0 for first shots, T1 for measured samples from each cavity
Handover
Tool drawing, steel certificate, hardness record, T1 report, process sheet
02

The part, and what it asks of the tool

A thin wall moves the difficulty from the outside of the block to the inside of it.

The part is a slim tube with a thin wall and a closed profile. Most of the machining time on a tool like this goes into the core, not into the plate. The plate carries the outline; the core decides the wall.

The cavity side forms the outer surface and the parting line. The core side carries a long, slim core that has to survive injection pressure, cool from the inside, and release without dragging on the wall it has just formed. Thirty-two of those cores sit in one block, and each one has to behave like the other thirty-one.

That shape changes the priorities. Wall thickness matters more than the outside profile, because a core that shifts by a few hundredths of a millimetre changes the wall on both sides at once. Cooling matters more than metal removal rate, because a hot core lengthens the cycle and pulls the part out of shape when it is ejected.

The tool in the photograph is the finished article: cavity block on the right, core side on the left, water fittings on the side of both plates, guide pillars at the four corners. What the photograph cannot show is the sequence that produced it, which is the rest of this page.

Close view of the 32-cavity block after polishing, showing four columns of eight slender cavities, runner channels and the water fittings on the side of the plate
Cavity block after polishing. Four columns of eight cavities, with the cooling fittings on the side. The block is measured as one part, against one datum, before the core is fitted.
03

What the buyer put in writing

The order was fixed on a drawing, not on a description. These were the acceptance points.

RequirementWhat it meant in the toolWhere it was checked
Cavity dimensionsThe steel dimensions that form the part, held to ±0.01 mm where the tool drawing marks itCMM on the cavity block
Cavity-to-cavity consistencyEvery cavity measured against the same datum, not against its own referenceCMM comparison list, cavity by cavity
Core and cavity fitCore position, guide clearance and shut height after assemblyFit check and pin gauges at assembly
Wall thicknessCore position inside each cavity, not the nominal wall aloneSample measurement at T1
SurfacePolish on the working faces, no rounded edge at the parting lineVisual against the agreed sample
Gate and vestigeGate position and the finish left on the part after trimmingFirst shots, then trimmed samples
DocumentationSteel certificate, hardness record, dimensional report, trial reportHandover pack

Acceptance points for this tool. The drawing numbers behind them stay with the customer.

Nothing in this table is a promise for another part. A 32-cavity tool for a different wall, a different resin or a different press will carry a different set of numbers, and those are agreed at order.
04

Five places this tool could go wrong

None of these are solved by machining harder or polishing longer. They are solved in design, sequence and measurement.

  1. A slim core bends under pressure

    A long core acts like a beam. Injection pressure pushes it sideways, the wall on one side thickens and the wall on the other thins, and the part is out of tolerance in a way the plate cannot show. The answer starts before the first cut: core support, gate position and fill balance. A stiffer core that still fills unevenly moves the problem, it does not remove it.

  2. Cavity 27 is not cavity 1

    Thirty-two cavities mean thirty-two versions of the same dimension. If each cavity is cut and checked against its own reference, the tool can pass at the bench and still send rejects down the line. One datum, one comparison list, and the same characteristics measured on every cavity is what makes the block one tool instead of thirty-two tools in a frame.

  3. Alignment across a long fit

    The core has to enter the cavity with clearance small enough to hold the wall and large enough to survive a warm tool. The guide pillars set the position; the fit sets the rest. On a deep core, a small tilt at the base becomes a large offset at the tip, so the alignment is checked at assembly, not assumed from the machining report.

  4. Polishing a deep pocket without moving the edge

    Polish removes steel. Hand work at the bottom of a deep cavity can round the edge at the top and change the outline of the part. The allowance is left before the finishing cut, the edge is protected during polishing, and the working faces are worked in the draw direction so the part releases instead of dragging.

  5. Fill balance across four columns

    A runner that fills the first column early and the last column late gives different shrinkage along the block: the early cavities sink, the late ones burn or short. Venting has to follow the fill pattern, and the runner is sized for the last cavity, not the first. This is settled in the flow review, before steel is cut.

05

Decisions that shaped the build

Five choices carried most of the risk on this tool.

Core and cavity as a pair

The two halves were machined and measured together. A cavity dimension only means something next to the core dimension that answers it, so treating them as two independent parts invites a fit that has to be corrected by hand. The pair is the unit of work, and the pair is the unit of inspection.

One datum through the pair

The datum was set once and carried through rough machining, finishing, EDM and measurement. Changing the reference between operations is how a block ends up correct in each step and wrong as a whole. On a 32-cavity layout, that error shows up as a drift across the block, not as a single bad cavity.

Three axes where three axes are enough

Most of the cavity and core work on this tool ran on three axes, with 3+2 indexing for the angled walls. Five-axis was used where the cutter had to reach a wall without tilting the part. A mold does not need five axes on every face, and pretending otherwise adds cost without adding accuracy.

Polish planned as a dimension

Polishing stock was left in the finishing cut, and the sequence ran from the deepest face outward so the edge stayed where the drawing put it. Polish is a dimensional operation on a tool like this, not a cosmetic step at the end.

A trial plan before the first cut

Before steel was cut, the trial was defined: which cavities, which characteristics, which instrument, and what would count as a pass. That plan decides where the steel-safe allowance is left, because a dimension that cannot be moved later cannot be corrected at T1.

Core side of the mold with long slender cores in four columns, guide pillars and cooling connections, photographed on the assembly bench
Core side before assembly. The long cores carry the inside of the part; the guide pillars at the corners set the position of the two halves relative to each other.
On machine choice. If a wall can be reached with three axes and a good fixture, five-axis does not make it more accurate. The geometry decides the route, and the route is written down before the steel is ordered.
06

Build sequence

Nine stages, in the order they ran on this tool.

  1. Drawing review and DFM

    Draft, wall, gate, ejection and the critical dimensions reviewed together. The issue list is agreed with the customer before steel is cut.

  2. Tool design and 2D

    Assembly, parting line, cooling layout, ejection and the dimension chain. The drawing that the shop works to, not the part drawing.

  3. Steel order and incoming check

    Grade and hardness range confirmed against the resin and the volume. Mill certificate and grade marking checked on receipt.

  4. Rough machining and stress relief

    Stock removed in stages, with stress relief before finishing so the block does not move after the last cut.

  5. Heat treatment

    To the specified range at a qualified supplier. Hardness verified on the part, with the record returned to the project file.

  6. Finish milling and grinding

    Three-axis and 3+2 work on the cavity and core, five-axis where the wall needed it. Locating and mating faces ground.

  7. EDM

    Wire EDM for sharp-cornered profiles and inserts, sinker EDM for detail a cutter cannot reach. Recast layer removed before polishing.

  8. Polishing and fitting

    Working faces polished to the agreed finish, edges protected, slides and ejectors fitted, cooling circuits pressure tested.

  9. Trial and release

    T0 on the intended press with the intended resin, then T1 with samples from each cavity measured. Corrections cut, report updated, tool released.

07

Steel and heat treatment

The steel choice is a wear decision. The certificate is what makes it a fact.

This tool was ordered in hardened tool steel, with the grade and hardness range fixed in the order. The grade is chosen against three things: what the resin does to the steel, how many cycles the tool has to survive, and how much polish the part needs. A glass-filled grade wears a cavity, a corrosive grade attacks it, and a high-polish surface needs a steel that can take the finish without tearing.

Hardness is checked after heat treatment, on the part, at a stated place, and recorded next to the mill certificate. Arriving hardness is not specified hardness: a block can arrive marked correctly and still measure outside the range after treatment, which is why the check is done rather than assumed.

Two details decide whether the hardness survives the rest of the build. Stress relief has to happen before finishing, or the block moves after the last cut. EDM recast has to be removed before polishing, or the surface looks finished and fails at the first thousand cycles.

Grade familyTypical use on a tool
P20General cavity and core work, machines well, holds a good polish
718HBetter homogeneity and polishability than plain P20, visible parts and larger blocks
H13Wear resistance and hot work, abrasive resins and high-volume tools
S136Corrosive resins such as PVC, and high-polish surfaces
NAK80Fine texture and appearance parts, good polishability
45# / S50CStructure plates only, never a cavity or core material

The family used on this tool is recorded in its order, with the hardness range and the place it is measured.

08

Inspection: steel first, then the part

A cavity that measures correctly in steel can still produce a part out of tolerance. Both stages are measured, on the same characteristics.

CheckMethodRecord
Cavity and core dimensionsCMM on the finished steel, nominal against measuredDimensional report, dimension by dimension
Cavity-to-cavity comparisonEach cavity measured against the same datumOne list covering all 32 cavities
Core and cavity fitPin gauges and fit check after assemblyAssembly record with clearances
Cooling circuitsPressure test on both platesTest record with pressure and time
HardnessTester on the part, at the stated placeHardness record with mill certificate
Wall thickness and part dimensionsSamples from every cavity, same characteristicsT1 report, cavity identified per sample
Surface and edgesVisual against the agreed samplePolish and texture note

The measuring instrument is named in the report for a reason: a number without a method cannot be checked by anyone else.

T0 and T1 are different events. T0 is the first run of the assembled tool: it shows whether the tool closes, fills, cools and ejects, and the shots are usually checked visually. T1 is the measured run: samples from every cavity are measured against the drawing, and the steel-safe allowance is confirmed before corrections are cut.
No blanket tolerance is quoted for this tool, and no inspection claim is made for parts that were not sampled. A report covers the characteristics and the cavities it lists.
09

What was handed over

A tool is only finished when the next person can run it without calling the person who built it.

Cavities32Four columns of eight
Cavity work±0.01 mmOn marked dimensions
TrialT0 + T1Cavity-by-cavity samples
ReleaseAfter T1Corrections cut first

The tool was released after the trial was approved. The report from that trial lists each cavity against the same characteristics, so a later question about a dimension can be settled with a record rather than a memory.

The handover pack for this build followed the same list used on other tools: the tool drawing, the steel certificate, the hardness record, the T1 report with cavity identification, the process sheet used at trial, and the maintenance points that matter for this geometry.

Two items are deliberately absent from this page. The customer and the application are not published, and the part drawing, resin grade and order volumes stay in the project file. Publishing a tool without publishing someone else's drawing is the line we hold.

CMM probe measuring the cavity block of the injection mold on a granite table, with the dimensional report open beside it
The cavity block on the CMM. Each cavity is measured against the same datum, and the results are listed in order rather than averaged into one figure.
10

Where the work happened

Machining, EDM and polishing of the cavity and core run in our mold shop, so a correction does not wait for a third party.

Five-axis machining centre cutting a hardened mold insert, with coolant and fine chips visible around the block
Finishing a cavity insert. Most faces on this tool were reached with three axes or 3+2 indexing; five-axis was used where the cutter had to reach a wall without tilting the part.

Machining, EDM and polishing of the cavity and core are done in our mold shop. That matters for a multi-cavity tool: when T1 shows a dimension that needs to move, the correction is a scheduling decision rather than a negotiation with an outside shop.

Heat treatment and texture work go to qualified suppliers, and the records come back to the project file. We do not describe those steps as if they happened under our roof, because the certificate is what the customer will rely on later.

The result is a build where the parts that need to stay together stay together, and the parts that need a specialist get one.

Polish is where a tool like this is most often hurried, and where a hurry is most expensive. A rounded edge at the parting line shows on every part for the life of the tool, and no amount of later inspection removes it.

The working faces are polished in the draw direction, the edges are protected, and the finish is checked against a sample rather than described in words. If the part needs a texture, the texture is agreed before the steel is finished, because texture and polish take different allowances.

Polished mold insert with a single slender cavity, polishing stone, compound and a clean cloth beside it on a dark bench mat
Polishing stock is left in the finishing cut. On a deep cavity the work starts at the bottom and moves outward so the edge at the top stays where the drawing put it.
12

Questions this page usually raises

Short answers, written for the person who has to defend the decision to a colleague.

What is a 32-cavity injection mold?
A 32-cavity mold is a single tool that forms 32 parts in one cycle. The cavities sit in one block, fed by a runner, and the core side carries 32 matching cores. The value is output per cycle and a lower part price at volume. The cost is a longer build, a larger press, and a tighter requirement for consistency between cavities, because every cavity has to hold the same dimension against the same datum.
Why use 32 cavities for a small part?
Small parts take little shot weight, so one cycle can carry many of them without exceeding the press. The decision is usually volume against tool cost: more cavities lower the part price but raise the tool price, the press size and the risk that one cavity drifts. On this project the layout was four columns of eight, which keeps the runner short and the block compact.
What tolerance applies to the cavity?
±0.01 mm applies to the cavity dimensions marked on the tool drawing, not to every surface. Surfaces that form the part are held to the drawing; clearance faces, pockets and water lines have their own, wider tolerances. The molded part has a different tolerance again, because shrinkage, gate position and cooling decide the final size. Quoting one number for the whole tool is how projects get into trouble.
How is cavity-to-cavity variation checked?
Every cavity is measured on the CMM against the same datum, and the results are listed cavity by cavity, not averaged. At trial, samples from each cavity are measured on the same characteristics. A tool can look correct when one sample is checked; the list is what shows whether cavity 27 is drifting. On this tool that list is part of the T1 report.
What does hardened tool steel mean on this tool?
It means the cavity and core were ordered in a hardened mold steel rather than a low-carbon block, and the grade and hardness range were fixed in the order. Hardness is checked on the part at a stated place and recorded with the mill certificate. Arriving hardness is not the same as specified hardness, so the check is done after heat treatment, not assumed from the supplier label.
Which mold steel grades do you work with?
P20 and 718H for general cavity and core work, H13 for wear and hot work, S136 for corrosive resins and high polish, NAK80 for fine texture and appearance parts, and 45# or S50C for structure plates only. The grade follows the resin and the volume. Glass-filled grades wear a cavity, corrosive grades attack it, and those are different problems with different answers.
Why polish the cavity, and how is the finish controlled?
Polish does two things: it releases the part and it sets the surface the part will copy. On a deep cavity, polishing removes steel, so allowance is left before the finishing cut and the edges are protected. Working faces are polished in the draw direction. The finish is agreed against a sample or a standard, not described as high polish in an email.
What happens at T0 and T1?
T0 is the first run of the assembled tool: the purpose is to see whether the tool closes, fills, cools and ejects, and the shots are usually checked visually. T1 is the measured run: samples from each cavity are measured against the drawing, the steel-safe allowance is confirmed, and corrections are cut before release. The definitions are written into the order, because trial numbers mean different things at different suppliers.
Can a mold be corrected after trial?
Yes, within the steel-safe allowance left for that purpose. Corrections are planned before the first cut: which dimensions can be moved, by how much, and in which direction. Once a tool is outside that allowance, a correction becomes a weld or an insert, and both are decisions the customer should see before they happen. The T1 report states which dimensions moved, how far, and whether a second measurement is needed after the correction.
Do you build the mold and run production?
The mold is built in our mold shop, and production can run on our presses. Some customers take the tool to their own plant; others keep it here and order parts. Both are normal. The handover pack is the same either way: tool, tool drawing, steel certificate, hardness record, trial report and process sheet. If the tool travels, the drawing set and the trial record travel with it, so the receiving plant starts from the same numbers.
What do you need to quote an injection mold?
A part drawing or 3D model with tolerances and the surfaces that matter, the resin grade, the volume you expect in the first year, the press you plan to run, the polish or texture requirement, and the documentation you need at handover. If the part is not final, say so: a DFM review before steel is cut is cheaper than a correction after trial.
How long does a multi-cavity mold take to build?
The calendar is set at order, against the scope. Design and DFM, steel delivery, rough and finish machining, heat treatment, EDM, polishing, fitting and trial are separate stages, and multi-cavity work adds cavity-by-cavity measurement. A single-cavity tool and a 32-cavity tool are not the same project even when the part is the same. We quote the date with the scope rather than promise a generic lead time.
Request for quotation

Send the drawing, not the description

A mold is quoted against a drawing, a resin and a volume. If you send those three, the reply can be specific about the cavity count, the steel, the trial plan and the documents you will receive. If the part is still moving, send it anyway and ask for a DFM review first.

What to include
  • Part drawing or 3D model, with tolerances and critical surfaces
  • Resin grade, and whether it is filled or flame retardant
  • Expected first-year volume and the press you plan to run
  • Cavity count you have in mind, or the target part price
  • Polish, texture or cosmetic requirement, with a sample if one exists
  • Documents needed at handover: steel cert, hardness, CMM, T1, PPAP
GC

Written by the Goldcattle mold shop. Xiamen Goldcattle Plastic & Metal Products Co., Ltd. has built molds and machined parts in Xiamen since 1998, under an ISO 9001:2015 quality system. This record was written from the tool build file: the tool drawing, the steel and hardness records, and the trial report.